Replacement of the Main Transformer at the Enfidha Cement Plant
Replacement of the Main Transformer at the Enfidha Cement Plant :
- Schneider Electric 25MVA 150/5,5 KV
Dismantling of the Existing Transformer.
Complete Commissioning of the Transformer:
- Installation and connection of the transformer.
- Analysis, filling, and treatment of transformer oil.
Execution of Electrical Tests on the Transformer:
- Measurement of the transformation ratio (Ratio Test).
- Measurement of winding resistance.
- Measurement of insulation resistance and polarization index.
- Dielectric tests and power factor measurement (Tan Delta).
- Short-circuit impedance measurement.
- Measurement of no-load and load magnetizing current.
Project Details
Project Owner :
SOCIÉTÉ DES CIMENTS D’ENFIDA
Project Manager :
PTD ENGINEERING
Location :
Enfida
Year :
2024