Construction of the Sousse Power Plant

Home 5 Our Projects 5 Construction of the Sousse Power Plant

Construction of the Combined Cycle Power Plant, Phase C and D, 480 MW :

  • TAMINI Electrical Transformers 480 MVA 225/15 kV

Complete Commissioning of the Transformer :

  • Installation and connection of the transformer.
  • Analysis, filling, and treatment of the transformer oil.

 

Execution of electrical tests on the transformer :

  • Measurement of the transformation ratio (Ratio Test).
  • Measurement of winding resistance.
  • Measurement of insulation resistance and polarization index.
  • Dielectric tests and power factor measurement (Tan Delta).
  • Short-circuit impedance measurement.
  • Measurement of no-load and load magnetizing current.

Project Details

Project Owner:

Société Tunisienne de l’Électricité et du Gaz (STEG)

Project Manager:

ETELEC
Ansaldo Energia

Location:

Sousse

Year:

2016