Construction of the Rades Power Plant
Home Our Projects Construction of the Rades Power Plant
Construction of the Combined Cycle Power Plant, Phase C, 480 MW :
- BEST Electrical Transformers 420+220 MVA 225/15 kV.
- Commissioning of the 6.6 kV MV Electrical Substation
- Telephone and Intercom System
Commissioning of the 6.6 kV MV Substation:
- Testing and commissioning of the substation.
- Testing of control, command, and protection systems
Complete Commissioning of the Transformer:
- Installation and connection of the transformer.
- Analysis, filling, and treatment of transformer oil.
Execution of Electrical Tests on the Transformer:
- Measurement of the transformation ratio (Ratio Test).
- Measurement of winding resistance.
- Measurement of insulation resistance and polarization index.
- Dielectric tests and power factor measurement (Tan Delta).
- Short-circuit impedance measurement.
- Measurement of no-load and load magnetizing current.
Project Details
Project Owner:
Société Tunisienne de l’Électricité et du Gaz (STEG)
Project Manager:
GAMA SERVICE
Mitsubishi Power Europe, Ltd
Location:
Radès
Year:
2018